
Project Main Street
Rebuilding the roadway and improving pedestrian amenities from River to 6th Street, in partnership with Ketchum Urban Renewal Agency and Idaho Transportation Department
Main Street construction update (4th through 6th Street)
Construction on Main Street between 4th and 6th Street, which began on Monday, April 7, is progressing well, and electrical work and curb and sidewalk demolition are underway. The existing roadway has been removed, and unlike last year, the foundation will not require replacement. The sidewalk work on 2nd Street (south of the Culinary Institute) will be completed by the end of the week. Completion dates are still on schedule:
- Full street closure: April 7 to July 3
- Rolling sidewalk closures: April 7 to late July
We appreciate your continued patience as we work towards revitalizing the last section of Main Street.
(Updated 5-1-25)

(Updated 5-1-2025)
Elkhorn to River Street Project underway: The Idaho Transportation Department kicked off their Elkhorn to River Street Project on April 29. Stay in the loop on their progress at itdprojects.idaho.gov/pages/idaho75.
Sidewalk project on 5th Street between Main Street and Leadville Avenue: A sidewalk and retaining wall are being added to the south side of this street section for improved pedestrian and business access. Work is underway and is scheduled for completion by Memorial Day.
(Updated 5-1-2025)
Access to businesses will be open throughout construction. Through traffic should use the detour route: Serenade Lane to 2nd Avenue, 8th Street to Warm Springs Road, then 10th Street to Highway 75.
Please note that the bus will be operating on the detour route with the temporary bus stops along the route.
The phases outlined below are intended to give a general idea of construction plans. Slight shifts to these plans may occur throughout construction.

Phase 1 (complete)
April 1 to early May 2024 (complete)
2nd Street-4th Street
- April 3-30: Roadway closures for utility and infrastructure work
- April 19-May 2: Intermittent sidewalk closures (2nd to Sun Valley Road only) for demolition and infrastructure
Phase 2 (complete)
May 1 to early August 2024 (updated July 25, 2024)
2nd Street-4th Street
- May 1-late July: Roadway closures for demolition, foundation, and paving
- May 3-early August: Intermittent sidewalk closures for demolition, infrastructure, and paver installation

Note: Idaho Power will install a redundant power line during Phase 2 of Main Street construction that requires the following closures.
- April 29-May 24: Main Street between River and 2nd Street and 2nd Street from Main Street to Leadville
- May 25-June 9: 2nd Street from Leadville to East Avenue
- June 10-14: 2nd Street from East Avenue to Alpine Lane
- June 15-21: 2nd Street from East to Walnut Avenue
- June 24-July 3: 2nd Street from Walnut to Spruce Avenue
- July 8-26: 2nd Street from Walnut to Spruce Avenue and Spruce Avenue from 2nd to Sun Valley Road


Phase 3 (complete)
Late July to early October 2024 (updated July 25, 2024)
River Street-2nd Street
- Late July-mid September: Roadway closures for demolition, foundation, and paving
- Early August-early October: Intermittent sidewalk closures for demolition and paver installation
Phase 4
April to July 2025 (updated October 24, 2024)
4th Street-6th Street
- Roadway closures for demolition, foundation, and paving
- Intermittent sidewalk closures for demolition, infrastructure, and paver installation

All businesses are open and accessible during construction, and directional signage is located around construction areas.
Support local and score $15! Select Main Street restaurants and retailers adjacent to construction are once again teaming up with the city and offering free $15 vouchers to spend at their respective businesses from April 16 through July 14. Pick up your free voucher at the Ketchum Visitor Center (491 Sun Valley Rd.) during operating hours. Limit one voucher per person.
Participating businesses

Ketchum will be rebuilding the roadway and improving pedestrian amenities from River through 6th Street, in partnership with Ketchum Urban Renewal Agency and Idaho Transportation Department.
Project goals
- Rebuild the roadway
- Improve travel efficiency during peak travel times
- Reconfigure Sun Valley Road intersection by adding designated left turn lanes on Main Street
- Upgrade traffic signals to decrease unused “green” time
- Synchronize traffic lights for better traffic flow
- Improve ADA/pedestrian realm and safety at crosswalks
- Install bulbouts to decrease pedestrian crossing distance at corners
- Install raised intersection at Sun Valley Road for ADA accessibility and better view of pedestrians
- Address the issue of “no left turns” in Ketchum
Frequently Asked Questions:
Images of construction plans coming soon…